Spring 2015 Timeline

Timeline (as of 1/29/2015)

 

The current timeline is shown below. We will keep this timeline updated with any changes.

Milestone Begin Date End Date
Device Incentives Determined √
11/14/2014 11/14/2014
Recommended Incentives Approved √
01/16/2015 01/16/2015
Bid Specfications Meeting √
01/21/2015 01/21/2015
Forecasting Window √ 01/30/2015
02/18/2015
Invitation to Bid Released √ 02/23/2015 03/17/2015
Sealed Bids Due √ 03/17/2015 03/17/2015
Bid Evaluation Meeting √ 03/25/2015 03/25/2015
Award Recommendations Approved by CCISD √ 04/07/2015 04/07/2015
Notify Vendors of Awards √ 04/08/2015 04/08/2015
Negotiate Vendor Contracts 04/08/2015 04/14/2105
Open Incentivized Purchase Window 04/15/2015 08/14/2015
Continue Non-Incentivized Purchase Window 08/15/2015 09/30/2015
Audit/Verify Vendor Reports, Calculate Incentives 08/17/2015 10/30/2015
Distribute Incentive Checks 11/10/2015 11/24/2015